Earned Value (EV)

The budgeted value of the work actually completed at a point in time.

Earned Value (EV) is the budgeted cost of work physically completed at a given point. Expressed in dollars, it is calculated as EV = BAC × % complete, making it the central variable in Earned Value Management. EV feeds Schedule Variance (SV = EV − PV), Cost Variance (CV = EV − AC), the Schedule Performance Index (SPI = EV / PV), and the Cost Performance Index (CPI = EV / AC). EV measures work done against budget, not against what was actually spent — confusing it with Actual Cost is the common mistake. A project can run EV above AC (under budget) yet EV below PV (behind schedule), so always evaluate both variances together.

PlayPrepHQ study notes are written and reviewed against primary exam sources. How we create & review content →

Related terms

Back to Process